[2016] FWC 5694
FAIR WORK COMMISSION

STATEMENT


Fair Work Act 2009

s.156 - 4 yearly review of modern awards

4 yearly review of modern awards—Group 4 awards
(AM2014/250 and others)

JUSTICE ROSS, PRESIDENT

MELBOURNE, 15 AUGUST 2016

4 yearly review of modern awards – award stage – Group 4 awards.

[1] Section 156 of the Fair Work Act 2009 (the Act) requires the Fair Work Commission (the Commission) to review all modern awards every four years (the Review). In the Award stage of the Review the 122 modern awards have been divided into 4 groups. The awards allocated to Group 4 are listed at Attachment A to this Statement. As proposed in the 24 February 2016 Statement 1 the 40 awards in Group 4 will be dealt with in two tranches – sub-groups 4A, 4B & 4C and sub-groups 4D, 4E & 4F. A Statement and amended directions were issued on 10 May 20162 outlining the proposed timetable for dealing with the awards in Group 4. A further statement, issued on 15 July 20163, vacated the directions in relation to the Construction awards4 and varied the proposed timetable for the remaining matters.

[2] Due to the resource demands associated with the Review, the timetable for finalising the review of Group 4 awards has been further deferred as set out below.

Group 4A, 4B & 4C

[3] In the February 2016 Statement, claims to vary the provisions in the Construction awards were referred to Senior Deputy President Watson. A number of conciliation conferences were held before Senior Deputy President Watson, most recently on 2 August 2016. The Senior Deputy President has provided a Report which outlines the following process for determining the issues in respect of the Construction Group Awards:

[4] The amended directions of 10 May 2016 in respect to the Plumbing and Fire Sprinklers Award 2010, were varied to require the filing of submissions in reply by 3 August 2016.

[5] The amended directions of 10 May 2016 also required reply submissions on the drafting and technical issues in relation to groups 4A, 4B and 4C to be filed by 21 July 2016.

[6] These matters will be listed for hearing in November 2016. A notice of listing will follow in due course.

Group 4D, 4E & 4F exposure drafts

[7] In the Statement of 23 March 2016 5 it was proposed that a Full Bench deal with a number of issues in relation to the Broadcasting and Recorded Entertainment Award 2010. Following conferences before Senior Deputy President Hamberger6, these issues have been resolved and the remaining issues in this award will be dealt with by the main Group 4 Full Bench.

[8] The publication of exposure drafts for the awards allocated to Groups 4D, 4E and 4F has been deferred until October 2016. The directions in relation to filing material for these awards have been varied accordingly. The revised timeline for all of Group 4 is as follows:

Group 4 Awards

4A, 4B and 4C

 

3 August

Submissions in reply on drafting and technical issues in Plumbing award

To be advised

Submissions in reply on drafting and technical issues in On-site, Joinery and Mobile Crane awards

Late August

November 2016

Hearings re drafting and technical issues in Group 4A, B and C awards  (except On-site, Joinery and Mobile Crane awards)

4D, 4E and 4F

 

By 30 September

Mid October 2016

Group 4D, E and F exposure drafts (other than those being dealt with as part of Plain language exercise 7) to be published.

24 November

21 December 2016

Submissions on drafting and technical issues in Group 4D, E and F exposure drafts (other than those being dealt with as part of Plain language exercise)

19 January 2017

31 January 2017

Submissions in reply on drafting and technical issues in Group 4D, E and F exposure drafts (other than those being dealt with as part of Plain language exercise)

February 2017

February 2017

Hearings re drafting and technical issues in 4D, E and F

[9] Amended directions are attached.

[10] A mention will be held at 1.00pm on Wednesday 24 August 2016 to provide an opportunity for any interested person to raise any issues in respect of the programming of the review of the Group 4 awards, as set out in this statement. The Commission will be sitting in Sydney, requests for video links should be sent to chambers.ross.j@fwc.gov.au.

PRESIDENT

ATTACHMENT A—Group 4 awards divided by sub-group

    Award code

    Award title

    Matter No.

    Sub-group 4A

 

    Aboriginal Community Controlled Health Services Award 2010

    Aged Care Award 2010

    Children’s Services Award 2010

    Educational Services (Teachers) Award 2010

    Social, Community, Home Care and Disability Services Industry Award 2010

    Supported Employment Services Award 2010

    Sub-group 4B

 

    Air Pilots Award 2010

    Aircraft Cabin Crew Award 2010

    Airline Operations—Ground Staff Award 2010

    Airport Employees Award 2010

    Sub-group 4C

 

    Architects Award 2010

    Building and Construction General On-site Award 2010

    Electrical, Electronic and Communications Contracting Award 2010^

    Hydrocarbons Field Geologists Award 2010

    Joinery and Building Trades Award 2010

    Mobile Crane Hiring Award 2010

    Plumbing and Fire Sprinklers Award 2010

    Surveying Award 2010

    Sub-group 4D

 

    Amusement, Events and Recreation Award 2010

    Book Industry Award 2010

    Broadcasting and Recorded Entertainment Award 2010

    Journalists Published Media Award 2010

    Live Performance Award 2010

    Racing Clubs Events Award 2010

    Travelling Shows Award 2010

    Sub-group 4E

 

    Car Parking Award 2010

    Cemetery Industry Award 2010

    Food, Beverage and Tobacco Manufacturing Award 2010

    Funeral Industry Award 2010

    Pest Control Industry Award 2010

    Professional Employees Award 2010

    Water Industry Award 2010

    Sub-group 4F

 

    Dry Cleaning and Laundry Industry Award 2010

    Fast Food Industry Award 2010

    General Retail Industry Award 2010

    Hair and Beauty Industry Award 2010

    Hospitality Industry (General) Award 2010

    Mannequins and Models Award 2010

    Registered and Licensed Clubs Award 2010

    Restaurant Industry Award 2010

^ Note the Electrical, Electronic and Communications Contracting Award 2010 was incorrectly allocated to Group 4A in an earlier Statement.

ATTACHMENT B—REVISED DIRECTIONS

DIRECTIONS

fwc_logo


Fair Work Act 2009

s.156 - 4 yearly review of modern awards

4 yearly review of modern awards—Group 4
(AM2014/250 and others)

JUSTICE ROSS, PRESIDENT

MELBOURNE, 15 AUGUST 2016

It is directed that:

1. The drafting and technical issues in the Group 4A, 4B and 4C exposure drafts will be listed for hearing in November 2016.

2. On or before 4.00 pm on Wednesday 21 December 2016 each interested party is to file in the Commission submissions on the technical and drafting issues related to exposure drafts in Groups 4D, 4E and 4F (except the awards that are subject to the Plain language process).

3. On or before 4.00 pm on Tuesday 31 January 2017 each interested party is to file in the Commission submissions in reply on the technical and drafting issues related to exposure drafts in Groups 4D, 4E and 4F (except the awards that are subject to the Plain language process).

4. The drafting and technical issues in the Group 4D, 4E and 4F exposure drafts will be listed for hearing in February 2017.

5. All material should be sent to amod@fwc.gov.au.

6. Leave is granted to apply generally.

Note: Further directions will be issued in relation to the remaining awards in the Construction group following the determination of the substantive issues in these awards.

PRESIDENT

 1   [2016] FWC 1191; see also [2016] FWC 1838

 2   [2016] FWC 2924

 3   [2016] FWC 4781

 4   Building and Construction General On-site Award 2010, Joinery and Building Trades Award 2010, Mobile Crane Hiring Award 2010 and Plumbing and Fire Sprinklers Award 2010

 5   [2016] FWC 1838 para [9]]

 6   Report to the Full Bench

 7   See Statement of 11 August 2016 [2016] FWCFB 5621

Printed by authority of the Commonwealth Government Printer

<Price code C, PR584215>