MA000056 PR740736 |
FAIR WORK COMMISSION |
DETERMINATION |
Fair Work Act 2009
s.285—Annual wage review
Annual Wage Review 2021–22
(C2022/1)
CONCRETE PRODUCTS AWARD 2020
[MA000056]
Cement and concrete products | |
JUSTICE ROSS, PRESIDENT |
MELBOURNE, 28 JUNE 2022 |
Annual Wage Review 2021–22.
A. Further to the decision issued by the Expert Panel in the Annual Wage Review 2021–22 on 15 June 2022 [[2022] FWCFB 3500], the above award is varied as follows:
1. By deleting the table appearing in clause 16.2 and inserting the following:
Employee classification |
Minimum weekly rate
|
Minimum hourly rate |
$ |
$ | |
Level 1 |
812.60 |
21.38 |
Level 2 |
834.70 |
21.97 |
Level 3 |
865.20 |
22.77 |
Level 4 |
893.60 |
23.52 |
Level 5 |
940.90 |
24.76 |
2. By deleting the year “2021” in clause 16.5(b) and inserting “2022”.
3. By deleting the amount “$23.18” appearing in clause 18.2(b)(i) and inserting “$24.38”.
4. By deleting the amount “$15.45” appearing in clause 18.2(b)(ii) and inserting “$16.25”.
5. By deleting the amount “$0.61” appearing in clause 18.2(c) and inserting “$0.64”.
6. By deleting the amount “$3.09” appearing in clause 18.2(d) and inserting “$3.25”.
7. By deleting the table appearing in clause 18.2(e)(ii) and inserting the following:
In charge of |
$ per week |
Less than 3 employees |
23.57 |
3 to 6 employees |
30.88 |
More than 6 employees |
37.38 |
8. By deleting the amount “$0.61” appearing in clause 18.2(f)(i) and inserting “$0.64”.
9. By deleting the amount “$0.96” appearing in clause 18.2(f)(ii) and inserting “$1.00”.
10. By deleting the amount “$0.96” appearing in clause 18.2(f)(iii) and inserting “$1.00”.
11. By deleting the amount “$4.98” appearing in clause 18.2(g) and inserting “$5.24”.
12. By deleting the table appearing in clause B.2.1 and inserting the following:
|
Day |
Public holiday |
% of ordinary hourly rate1 | ||
|
100% |
250% |
$ |
$ | |
Level 1 |
22.02 |
55.05 |
Level 2 |
22.61 |
56.53 |
Level 3 |
23.41 |
58.53 |
Level 4 |
24.16 |
60.40 |
Level 5 |
25.40 |
63.50 |
13. By deleting the table appearing in clause B.2.2 and inserting the following:
|
Day |
Afternoon & night |
Non-successive afternoon & night1 |
Permanent night |
Saturday |
Sunday & public holiday | |
First 2 hours |
After 2 hours | ||||||
% of ordinary hourly rate2 | |||||||
|
100% |
115% |
150% |
200% |
125% |
150% |
200% |
$ |
$ |
$ |
$ |
$ |
$ |
$ | |
Level 1 |
22.02 |
25.32 |
33.03 |
44.04 |
27.53 |
33.03 |
44.04 |
Level 2 |
22.61 |
26.00 |
33.92 |
45.22 |
28.26 |
33.92 |
45.22 |
Level 3 |
23.41 |
26.92 |
35.12 |
46.82 |
29.26 |
35.12 |
46.82 |
Level 4 |
24.16 |
27.78 |
36.24 |
48.32 |
30.20 |
36.24 |
48.32 |
Level 5 |
25.40 |
29.21 |
38.10 |
50.80 |
31.75 |
38.10 |
50.80 |
14. By deleting the table appearing in clause B.3.1 and inserting the following:
|
Monday to Saturday |
Sunday – all day |
Rostered day off | ||
First 2 hours |
After 2 hours |
First 2 hours |
After 2 hours | ||
% of ordinary hourly rate1 | |||||
|
150% |
200% |
200% |
150% |
200% |
$ |
$ |
$ |
$ |
$ | |
Level 1 |
33.03 |
44.04 |
44.04 |
33.03 |
44.04 |
Level 2 |
33.92 |
45.22 |
45.22 |
33.92 |
45.22 |
Level 3 |
35.12 |
46.82 |
46.82 |
35.12 |
46.82 |
Level 4 |
36.24 |
48.32 |
48.32 |
36.24 |
48.32 |
Level 5 |
38.10 |
50.80 |
50.80 |
38.10 |
50.80 |
15. By deleting the table appearing in clause B.3.2 and inserting the following:
|
Monday to Sunday and public holidays |
% of ordinary hourly rate1 | |
|
200% |
$ | |
Level 1 |
44.04 |
Level 2 |
45.22 |
Level 3 |
46.82 |
Level 4 |
48.32 |
Level 5 |
50.80 |
16. By deleting the table appearing in clause B.3.3 and inserting the following:
|
Monday to Sunday |
Public holiday | |
First 2 hours |
After 2 hours |
||
% of ordinary hourly rate1 | |||
|
150% |
200% |
200% |
$ |
$ |
$ | |
Level 1 |
33.03 |
44.04 |
44.04 |
Level 2 |
33.92 |
45.22 |
45.22 |
Level 3 |
35.12 |
46.82 |
46.82 |
Level 4 |
36.24 |
48.32 |
48.32 |
Level 5 |
38.10 |
50.80 |
50.80 |
17. By deleting the table appearing in clause B.4.1 and inserting the following:
|
Day |
Public holiday |
% of ordinary hourly rate1 | ||
|
125% |
275% |
$ |
$ | |
Level 1 |
27.53 |
60.56 |
Level 2 |
28.26 |
62.18 |
Level 3 |
29.26 |
64.38 |
Level 4 |
30.20 |
66.44 |
Level 5 |
31.75 |
69.85 |
18. By deleting the table appearing in clause B.4.2 and inserting the following:
|
Day |
Afternoon & night |
Non-successive afternoon & night1 |
Permanent night |
Saturday |
Sunday & public holiday | |
First 2 hours |
After 2 hours | ||||||
% of ordinary hourly rate2 | |||||||
|
125% |
140% |
175% |
225% |
150% |
175% |
225% |
$ |
$ |
$ |
$ |
$ |
$ |
$ | |
Level 1 |
27.53 |
30.83 |
38.54 |
49.55 |
33.03 |
38.54 |
49.55 |
Level 2 |
28.26 |
31.65 |
39.57 |
50.87 |
33.92 |
39.57 |
50.87 |
Level 3 |
29.26 |
32.77 |
40.97 |
52.67 |
35.12 |
40.97 |
52.67 |
Level 4 |
30.20 |
33.82 |
42.28 |
54.36 |
36.24 |
42.28 |
54.36 |
Level 5 |
31.75 |
35.56 |
44.45 |
57.15 |
38.10 |
44.45 |
57.15 |
19. By deleting the amount “$772.60” appearing in clause C.1.1 and inserting “$812.60”.
20. By deleting the table appearing in clause C.1.1 and inserting the following:
Allowance |
Clause |
% of standard weekly rate |
$ |
Payable |
Industry allowance—Other than factories manufacturing tiles1 |
18.2(b)(i) |
3.0 |
24.38 |
per week |
Industry allowance—Factories manufacturing tiles1 |
18.2(b)(ii) |
2.0 |
16.25 |
per week |
First aid allowance |
18.2(d) |
0.4 |
3.25 |
per day |
Leading hand in charge of—Less than 3 employees |
18.2(e)(ii) |
2.9 |
23.57 |
per week |
Leading hand in charge of—3 to 6 employees |
18.2(e)(ii) |
3.8 |
30.88 |
per week |
Leading hand in charge of—More than 6 employees |
18.2(e)(ii) |
4.6 |
37.38 |
per week |
21. By deleting the amount “$20.33” appearing in clause C.1.2 and inserting “$21.38”.
22. By deleting the table appearing in clause C.1.2 and inserting the following:
Allowance |
Clause |
% of standard hourly rate |
$ |
Payable |
Cement or concrete allowance |
18.2(c) |
3.0 |
0.64 |
per hour or part thereof |
Bituminous sprayer allowance—Exterior surfaces |
18.2(f)(i) |
3.0 |
0.64 |
per hour or part thereof |
Bituminous sprayer allowance—Epoxy based materials allowance |
18.2(f)(ii) |
4.7 |
1.00 |
per hour or part thereof |
Bituminous sprayer allowance—Sand-blasting allowance |
18.2(f)(iii) |
4.7 |
1.00 |
per hour or part thereof |
Fork-lift operators allowance |
18.2(g) |
24.5 |
5.24 |
per week |
B. This determination comes into operation on 1 July 2022. In accordance with s.286(5) of the Fair Work Act 2009 this determination does not take effect in relation to a particular employee until the start of the employee’s first full pay period that starts on or after 1 July 2022.